The Mumbai-Ahmedabad bullet train project now stands at ₹2,02,797 crore, almost double its earlier estimate. As of March 2026, ₹92,761 crore has already been spent.
The original completion target was 2023. The revised timeline depends on awarding all contract packages.
India is shifting from Japanese Shinkansen rolling stock to indigenous bullet trains, and the first trainset will be dispatched in February 2027.
The initial plan called for Japanese Shinkansen technology, but the National High-Speed Rail Corporation (NHSRCL) has refused to provide correspondence with Japan over signalling systems, citing a non-disclosure agreement. NHSRCL also refuses to disclose whether Japan approved or objected to India-manufactured trains.