The Atal Setu–Mumbai-Pune Expressway Connector is 67% complete, promising a reduction of up to 90 minutes between South Mumbai and Pune. The six-lane elevated corridor bypasses the congested Panvel Main Junction, improving traffic flow and connectivity towards Navi Mumbai International Airport and other key destinations.
In the Chirle Section, foundation works are fully completed, with pier construction at 98% (153 of 155 piers constructed). Girder casting is largely finished, and deck slab works cover 117 of 240 spans, representing 49% completion. Reinforced Earth wall panel casting stands at 90%, and the Railway Overbridge (ROB) section is 85% completed.
In the Palaspe Section, pile-group foundations are 71% complete, with pier casting at 38%. The project features a third-level elevated configuration above existing roads and bridges, ensuring uninterrupted traffic movement and optimising the use of the current road corridor.